top of page

Norwest Pavilion
73-75 Windsor Road, Norwest NSW 2153

Project Updates
Oct 2026
Project Development & Leasing Progress
The project reached key milestones, including confirmation of the Norwest Pavilion name, appointment of a Construction Project Manager and Ray White as Sales & Marketing Agent, and progress towards finalising the childcare operator agreement.
Aug 2026
Construction Certificate & Build Tender
The project progressed to the Construction Certificate and build tender stage, with preparations underway for construction commencement.
Jul 2026
Land Settled
Settlement of the Norwest development site was completed, marking a key milestone in the project and paving the way for the construction phase.
Early 2026
Due Diligence & Contract Exchange
Due diligence was completed and the contract was exchanged, marking the commencement of the project acquisition process.
bottom of page